I need to add fifteen (15) working days to start dates, i.e. must exclude weekends.

Ex: April 1, 2010 + 15 working days = April 21, 2010 should be the answer to the formula.

Thank you.

C

1 response

rizvisa1 Posts 4478 Registration date Thursday January 28, 2010 Status Contributor Last seen May 5, 2022 766
Apr 8, 2010 at 05:03 PM
Use FUNCTION WORKDAY