Hi

I need to add fifteen (15) working days to start dates, i.e. must exclude weekends.

Ex: April 1, 2010 + 15 working days = April 21, 2010 should be the answer to the formula.

Thank you.

C

1 response

rizvisa1 Posts 4478 Registration date Thursday 28 January 2010 Status Contributor Last seen 5 May 2022 766
8 Apr 2010 à 17:03
Use FUNCTION WORKDAY