How to add 200 working days to a given date.

Solved/Closed
Bebs - 27 Feb 2018 à 08:24
Mazzaropi Posts 1983 Registration date Monday 16 August 2010 Status Contributor Last seen 24 May 2023 - 1 Mar 2018 à 06:21
Hello,



Please I want to know how I can add 200 working days to a specific date to get a new date
Related:

2 responses

Mazzaropi Posts 1983 Registration date Monday 16 August 2010 Status Contributor Last seen 24 May 2023 147
27 Feb 2018 à 09:58
Bebs, Good morning.

Scenario:

A1 --> SPECIFIC DATE --> eg.: 02/25/2018

Try to use:

B1 --> NEW DATE --> =WORKINGDAY(A1, 200)
B1 --> 11/30/2018

Format B1 as DATE

Is that what you want?

I hope it helps.
--
Belo Horizonte, MG - Brasil.
Marcílio Lobão
Hello Mazarropi,
Your solution was so on point! Thank you so much!!!
Mazzaropi Posts 1983 Registration date Monday 16 August 2010 Status Contributor Last seen 24 May 2023 147
1 Mar 2018 à 06:21
Bebs, Good morning.

Glad to have helped you.

Thanks for the feedback.
--
Belo Horizonte, MG - Brasil.
Marcílio Lobão